Chapter 148 SUBDIVISION AND LAND DEVELOPMENT. (updated 7-28-08)
Section 148-30 SANITARY SEWER DISPOSAL.
A. The
applicant shall provide the type of sanitary
sewer disposal facility determined by the town and the Health
Department to be
consistent with existing physical, geographical and geological
conditions.
Connection to the town sanitary sewer system shall be required, if
available.
Where town sanitary sewers are not available, the following types
of
sanitary sewage disposal facilities shall be employed in order of
desirability:
1. Community sanitary sewage system with a temporary sewage
treatment plant.
2. On-lot disposal with septic tank and drain field.
B. Sanitary
sewers, whether public, community or
on-site, shall be designed and constructed in strict accordance with
Department
of Health and/or State Water Control Board standards, as applicable.
C. The
sewer system and all service lines and
appurtenances, except the water meter, shall be installed in accordance
with
the plans and profiles prepared for the subdivision or development by a
professional engineer or licensed land surveyor and shall be approved
by the
Director of Public Works.
D. Sanitary
sewers shall not be used to carry
stormwater.
E. Where
the Town determines that the public sanitary
sewage collection system is accessible to the subdivision, the
connections from
the system to the property line of each lot in the subdivision shall be
made at
the time that the general site improvements are installed. Sewer
connection shall be installed by the applicant at his own expense in
accordance
with the design and specifications of the Town of Front Royal and shall
be
inspected by the Town in each instance.
(Ord.No.
8-06 Amended
7-24-06-Effective Upon Passage)
F. Sanitary
sewer lines installed in accordance with
plans and specifications approved by the town shall be required
improvements in
each subdivision or development to serve each subdivision lot, except
where the
town sewer lines are not available to the subdivision site and septic
tanks are
to be employed. The applicant at the time the sanitary sewer
lines are
constructed shall, at his own expense, install connections from the
sanitary
sewage lines to the property line of each lot in the subdivision not
then
served by the existing public sanitary sewage system. All
connections
shall be in accordance with the design and specifications of the Town
of Front
Royal and shall be inspected by the town in each instance. For
each
connection so made, the applicant, his successors or assigns shall
receive a
credit of five hundred dollars ($500.), which shall be deducted from
any future
sewage system tap-on fees charged by the town for that lot.